Total Project Cost: Parts + Materials + Labour = $23,500. Payback: 11 mos
- 55 out of 97 Toilets were replaced with 3.0L units
- Showerheads upgraded to 1.5 GPM
- Kitchen Aerators upgraded to 1.5 GPM
- Bath Vanity Aerators upgraded to 1.0 GPM
Leak Rate from 18.6% to 0.0%
Day |
Leak |
Total Volume |
Leak as % Total |
Thurs | 11,282 | 60,599 | 18.62% |
Fri | 7,497 | 48,615 | 15.42% |
Sat | 5,979 | 46,791 | 12.78% |
Sun | 5,878 | 58,749 | 10.01% |
Mon | 5,878 | 47,386 | 12.40% |
Tues | 2,008 | 43,580 | 0.46% |
Wed (*) | 0 | 16,466 | 0 |
Before: Consumption per unit / day = 0.62 m3 / unit / day. After: Consumption per unit / day = 0.45 m3 / unit / day
As a result of:
- replacing toilets that were > 3.0 L
- replacing shower heads and;
- installing aerators on kitchen sinks and bath vanities
The leak rate as a percentage of total consumption was reduced from 18% to 0%. In addition to eliminating the leaks, the per unit usage on a daily basis has dropped as a result of the more efficient toilets being rolled out. The building inventory of toilets are now all 3.0L with a mix of ProFlo (new ones installed) and Hennesy Henchcliffe (legacy 3.0 L already installed).
3.0L Toilet replacements throughout.
Bath Vanity Aerators upgraded to 1.0 GPM
Summary Daily Usage with Leak Rate Reduction
- Leak rate dropped from 18% to 0%
- Daily volume dropped from 60k / day to approx 40k / day
60 Day Snapshot : Oct 7th Completion Date
- Drop in daily consumption
- Elimination of leak rate by address toilets, showerheads and aerators
- Before / During and After Installation was Oct 4th – Oct 7th, 2021
Pre Retrofit Weekly Pattern
Post Retrofit Weekly Pattern – Notable drop in off peak usage
24 Hour Usage Pre Retrofit
- 17.7% Leak rate
- Avg Flow 41.9 L / min
24 Hour Usage Post Retrofit
- Drop in overall usage. Average Flow 25.6L / min
- Significant periods in off peak with no water usage. Zero (0) % leak rate